Air Raising Process Dome Roof Tank

October 29, 2009 by ferrysibarani

Sequential pictures below are the air raising process of a dome roof tank in Brunei Methanol Project, Brunei Darussalam. The tank is Product Methanol Tank with 63 metres inside diameter, 18 metres shell height and 50.4 metres radius dome roof. The air raising process was done on April 27th, 2009.

In this project, Brunei Methanol Company, Sdn. Bhd. is the owner, Mitsubishi Heavy Industries, Ltd. is the main contractor, PT. Rekayasa Industri is the sub-contractor, where as Consortium of Adinin Works & Engineering and PT. Bangun Bejana Baja is the manufacturer of 15 units KD Tanks.

Air Tight Test

This picture was the air tight test for checking the roof air sealing. It was done one day before the air raising process to ensure there was no leak in the air seal. A group of people were left inside and the tank pressurize with air by blower. After the roof float a few centimetres and no leakage or folded seal found then the test was finished.

Team gathering early morning

One day after the air tight test, the air raising was started. All crew was come to site in early morning.

Tool box meeting

The tool box meeting to ensure all crew knew their position and when they should do their job.

Air blower & air box access

These were the equipment to raise the roof. There are 4 sets (tandem) of blower which powered by separated generator, and an air box as the access to enter or exit the tank. In the process not all the blower used to pressurize the tank, 1 set was used as a back-up blower.

Balancing wire installation

This was the view of inside tank before air raised process. Inside the tank there were lamps to brighten inside, manometer as internal pressure indicator, and balancing wire fully installed.

Double block installation

This is double block for the rail of balancing wire. One wire sling come from above top shell through the roof and continue to the opposite side of roof tank then going down and fixed to the lower shell. There are 8 pair of double block to guide 16 balancing wire.

Double block, balancing wire, plastic seal

The complete set of double block, balancing wire and air seal.

Completed preparation

The complete set of inside tank preparation with continuous air seal around tank.

T-frame balancing wire

On of the equipment outside tank was the T-frame. This part was to guide the balancing wire from inside tank and fixed the end of wire to outside shell. There are 16 T-frame to guide 16 balancing wire.

Balancing wire with load indicator

4 numbers of the balancing wire were equipped with load cell indicator. This equipment was electrically connected to processor (computer) to show the tension of the balancing wire.

Laser level indicator

4 numbers of laser level indicator placed around tank, of course to indicate the position of the roof during floating, and were connected to computer in the control room.

Reflector laser level indicator

This is the reflector of laser level indicator.

Finish preparation for air raising

After ensure all the preparation were complete, include the flag of the involved party, the air raising can be proceed.

Air raising in progress

This was showing the roof floating more than half way. Approximately more 5 metres before the roof touching the tension bar.

Air raising in progress 2

The roof almost touching the tension bar and all crew already came to their position.

Worker ready to fit-up the roof

The fit-up of roof to tension bar can be started right after the roof touch the tension bar. In this process no welding was allowed before the entire jig were installed. This was to avoid the air seal got burn because of the torch from welding.

Fit-up on progress

Another side of the tank during air raising process. One special platform provided for better view of commander to make instruction.

Fit-up on progress 2

Fit-up process started with jig and horse-only without any welding, right after the roof touched the tension bar.

Fit-up jig and horse shoe

The installed jig and horse shoe. There are 96 set of jig required, each for one roof plate section.

Fit-up roof to tension bar

After completed all jig, fit-up for flattened roof plate to tension bar started. U-bar and bullpen used during this process.

Welding roof to tension bar

After roof fit-up completed, welding roof plate to tension bar can be started. One single pass weld minimum required before the jig can be removed from roof.

Completed air raising dome roof

After completed one pass welding of roof to tension bar, it was save now to leave the tank, and take a lunch break. The lifting itself take time only 2 hours, but the whole process started from 6 o’clock in the morning and finished at 12 o’clock.

Air raising team

This is the team who involved during the air raising process. Posed on the top of dome roof, without me who was taken the picture at that time. 😦 Cheers!!

Advertisements

Like this:

Like Loading...

Posted in Work Area | Tagged Air raising, blower, dome roof, Tank |

  • October 2009
    M T W T F S S
    « May   Feb »
     1234
    567891011
    12131415161718
    19202122232425
    262728293031  
  • Pages

    • About
  • Recent Posts

    • The joke called “Gay Pride Parade” July 10, 2015
    • Tsurugaoka Hachimangu Shrine February 29, 2012
    • 10% – 90% of Your Life February 16, 2012
    • Using Google Maps to Find Address and Route. February 11, 2012
    • Air Raising Process Dome Roof Tank October 29, 2009
    • Dome Roof with Internal Floating Roof October 23, 2009
    • One lie leads to another May 8, 2009
    • Keep Smiling..!! :D November 28, 2008
  • Categories

    • ferrysibarani
      • The joke called “Gay Pride Parade”
      • Tsurugaoka Hachimangu Shrine
      • 10% – 90% of Your Life
      • Using Google Maps to Find Address and Route.
      • Air Raising Process Dome Roof Tank
  • Advertisements

Blog at WordPress.com.

WPThemes.


Cancel
%d bloggers like this: